Subcontract cycle time: supplier cleared to PO issued
From supplier clearance to PO issued, Fauxmed subcontracts take an average of 32 business days. Only about 3 of those days involve active work, and each subcontract goes through an average of 3.4 redline passes.
Every day in this segment delays supplier kickoff. Over the last ten customer programs, four missed the customer's first delivery date, and in each one this segment was the longest wait before kickoff. Faster subcontracting protects delivery commitments to customers like the hospital network, and the relationships that renew them.
Cut average cycle time from 32 to 18 business days, and redline passes from 3.4 to 2.0 or fewer, within six months of charter approval.
| Metric | Role | Baseline | Target |
|---|---|---|---|
| Cycle time, cleared to PO issued | Primary | 32 days | 18 days |
| Redline passes per subcontract | Secondary | 3.4 | 2.0 or fewer |
| Contract modifications within 90 days of execution | Guardrail | 12% | No increase |
| Supplier claims on contract terms | Guardrail | 6% | No increase |
- Drafting, redline review, and final terms
- Routing and queues for tiered approvals
- The handoff from Legal to Finance
- Timestamping each step for measurement
- Approval dollar thresholds and authority levels, which are policy
- Supplier selection and sourcing
- Kickoff, delivery, and acceptance
- Supplier-side review time: tracked, but not controlled
- SponsorVP of Operations
- Process ownerDirector of Contracts
- Green Belt leadMe
- Core teamLegal, Finance approvals, Procurement
- As neededIT, for timestamp automation
- Baseline dates come from email, so the first measure is approximate
- Supplier response time is outside Fauxmed's control
- Legal has limited capacity for project work