How I Work: Subcontracts · A sample engagement

One task order. Three subcontracts. Every promise flows down.

This is the infusion pump program from How I Work: Lean. The regional hospital network is part of a federal health system, and Fauxmed's contract is a task order: deliver, install, and train staff on new infusion pumps across 40 clinics in 18 months. Fauxmed is the prime. It does not build the equipment, run the installs, or teach the classes.

So everything Fauxmed promised the government now has to be promised by someone else.

The supplier has to meet the same quality bar, the same schedule, the same security and labor rules, and the same reporting. If any of them misses, the health system does not see the supplier. It sees Fauxmed.

Firm-fixed-price

Sampleton Devices

Supplies the infusion pumps, delivered in three clinic waves.

$4.1M
Time and materials

Imaginary Field Services

Installs the pumps and connects them to each clinic's systems.

$1.2M ceiling
Fixed-price, milestone payments

Hypothetical Learning

Trains clinic staff. A small business.

$380K

How I Work: Lean fixed how long it takes to get a subcontract signed. This page shows what goes into each one, and what happens after, following all three subcontracts from selection to closeout.

At each stage I show the work product, the reasoning behind it, and the judgment call that mattered most: the point where the obvious answer was not the right one.

Fauxmed Supply Co., its customer, and every supplier are fictional. The methods are real. All figures are sample data.

Stage 01 · Pre-award

Choosing who to trust with a promise you already made.

Three companies bid on the field services work. The cheapest bid was not the best value, and the best score still needed conditions before anyone set foot in a clinic.

What this shows

Best-value source selection with criteria set before proposals arrive, a supplier risk review with hard stops, and choosing the contract type that puts each risk where it belongs.

Selection

Criteria and weights were fixed before any proposal was opened

Otherwise the criteria quietly bend toward whichever bid someone already likes. Each bidder is rated 1 to 10 per criterion, then weighted.

BidderTechnical
30%
Past performance
25%
Price
25%
Risk
10%
Small business
10%
Score
Imaginary Field Services897847.60
Notreal Install Group7696107.45
Placeholder Technical678546.45
The judgment call

The two top scores were 0.15 apart. A score that close is a tie, not a decision.

ChallengeNotreal was 9% cheaper and a small business. Choosing the higher price needs a reason that would survive an audit.

DecisionImaginary, on a written trade-off: its past performance was on multi-site rollouts of this size, and Notreal had never run more than 12 sites at once. Small business goals were met through the training subcontract instead.

Risk analysis

Risk analysis, in two layers

First, is each supplier safe to award? Then, what could go wrong across the whole subcontract portfolio, and who is watching for it?

SupplierMain concernCondition before awardVerdict
Sampleton DevicesThe pumps' network module could contain prohibited telecommunications componentsComponent certification received and reviewed by ComplianceGreen at award
Imaginary Field ServicesRevenue concentration; no written safeguarding planApproved safeguarding plan before any clinic accessConditional
Hypothetical LearningA small business with limited cash reserves for an 18-month effortMilestone payments and accelerated payment terms to protect its cash flowConditional

Deep dive: Imaginary Field Services

Some checks are hard stops. Failing one means Hold, whatever the score. The rest decide between Green and Conditional.

  1. Federal exclusions checkPass · hard stopNot debarred or suspended. Checked again before award, not only at proposal.
  2. Financial stabilityConditionalOne customer is 40% of revenue. Losing it mid-project would strain the company.
  3. Capacity for 40 sitesGreenSix install crews and a regional dispatch team.
  4. Data handlingConditionalTechnicians will touch clinic networks. No written safeguarding plan yet.
  5. InsuranceGreenMeets the playbook floor for this tier.
  6. Key personnelGreenNamed project manager with similar federal work.

Verdict

ConditionalAward with conditions

Award, but no technician enters a clinic until an approved safeguarding plan is on file. Financial health is re-checked each quarter, with a backup installer pre-qualified in case it slips.

Every condition has an owner and a date, so "Conditional" cannot quietly become "Green" by default.

Subcontract risk register

Each risk is scored for likelihood and impact from 1 to 5. The product sets the order. Every risk has an owner, a mitigation already in place, and a trigger that says when to act.

RiskLIScoreOwnerMitigationTrigger
Older clinic buildings drive installation overrun4416SubcontractsPer-clinic not-to-exceed; site surveys before each waveForecast exceeds ceiling
An equipment wave ships late or incomplete3412ProgramTwo-week buffer between delivery and install crewsAny shortage at receipt
Prohibited telecom component found in pumps2510ComplianceCertification before award; clause flowed downAny supplier disclosure
Patient data exposed during installation2510ComplianceSafeguarding plan; privacy terms; supervised accessAny incident, reported immediately
Small business trainer strained for cash339FinanceMilestone and accelerated paymentsLate invoice or staffing gap
Key installer personnel leave339SubcontractsKey personnel clause; backup installer pre-qualifiedSubstitution notice received

The register is reviewed monthly with Program and Finance. Scores move as conditions change, and a closed risk stays on the list with how it was closed.

Structure selection

Contract type follows where the uncertainty is

The type decides who carries the cost if things take longer than expected. Each subcontract got the type that matched what could and could not be known up front.

SubcontractWhat is knownTypeWho carries cost risk
EquipmentExact units, specifications, and delivery wavesFirm-fixed-priceSupplier
InstallationNumber of clinics, but not each building's condition until crews arriveTime and materials, with a ceilingFauxmed, up to the ceiling
TrainingCurriculum, class count, and outcomes can be defined in advanceFixed-price, paid on accepted milestonesSupplier
The judgment call

Fauxmed's own task order is fixed-price. A time-and-materials subcontract underneath it moves the risk onto Fauxmed.

ChallengeIf installs run long, the customer pays Fauxmed the same price, and Fauxmed pays the supplier more.

DecisionKeep time and materials, because forcing a fixed price on unknown site conditions would only buy a padded quote. Contain it instead: a hard ceiling, a not-to-exceed amount per clinic, and burn monitoring with triggers, shown in Stage 03.

How I got there

  1. Fixed criteria and weights before opening proposals, and wrote the trade-off down when the result was close.
  2. Ran risk analysis in two layers: each supplier before award, with hard stops and dated conditions, and a scored risk register for the whole portfolio.
  3. Chose each contract type by asking where the uncertainty sits, then contained the risk the prime contract could not absorb.

Stage 02 · Award

The paper is where the promises become enforceable.

Drafting decides what flows down, negotiation decides what it costs, and the milestone schedule decides what Fauxmed pays for and when.

What this shows

A flow-down matrix built clause by clause, a negotiation documented against an independent estimate, and milestones where payment follows proof.

FAR compliance checks

The required checks, by FAR reference

What the prime has to verify or flow down for each subcontract, where the requirement comes from, and how it is checked. Several apply only above dollar thresholds that change over time, so thresholds are looked up at award, not memorized.

FAR referenceRequirementWhen it appliesHow it is checked
9.4 · 52.209-6Do not subcontract with debarred, suspended, or excluded partiesSubcontracts above the clause thresholdExclusions search at proposal and again just before award
9.104-4The prime determines its subcontractors' responsibilityEvery subcontractDocumented review of capacity, integrity, and financial health
15.404-3Prime performs price or cost analysis of subcontract proposalsEvery negotiated subcontractNegotiation memorandum with the basis for each price
15.403-4Certified cost or pricing data, unless an exception appliesAbove the threshold, without adequate competitionThreshold and exception check before negotiation
44.2 · 52.244-2Advance notice and consent to subcontractWhen the prime contract requires it, for example time and materialsConsent request filed and approved before award
44.3Purchasing system that can pass a government reviewWhen the prime's sales to the government are large enough to be reviewedFile built to the review standard from the start
19.7 · 52.219-9Small business subcontracting plan and reportingLarge-business subcontracts above the thresholdPlan on file; reports filed on schedule
52.232-40Accelerated payments to small business subcontractorsWhere the prime contract includes the clausePayment terms set in the subcontract
4.21 · 52.204-25No prohibited telecommunications equipment or servicesAll subcontractsSupplier certification; flowed down
4.19 · 52.204-21Basic safeguarding of covered information systemsSuppliers that handle federal contract informationSafeguarding plan reviewed before access
3.502 · 52.203-7Anti-kickback proceduresSubcontracts above the clause thresholdFlowed down; gifts and fees policy acknowledged
22.8 · 52.222-26
22.17 · 52.222-50
Equal opportunity; combating trafficking in personsSubcontracts generallyFlowed down; certifications on file
4.7 · 52.215-2Records retention and audit accessWhere the prime clause requires it, including time and materialsRetention schedule set; audit clause flowed down

References use the long-standing FAR numbering. The FAR is being rewritten through the Revolutionary FAR Overhaul, with class deviations already issued and further rules proposed in 2026, so every check is confirmed against current text and the agency's deviations at award.

Automated checks

From checklist to system rules

A checklist depends on someone remembering to use it. A rule in the subcontract system runs every time, so the check cannot be skipped under deadline.

CheckRuns whenUsesIf it fails
Exclusions and registration statusAt proposal, at award, then monthlyThe federal exclusions and registration recordsAward blocked; active subcontract flagged to Subcontracts and Legal
Required clauses selectedWhen type, value, and supplier size are enteredA clause rules table kept by ComplianceDraft cannot be generated with a required clause missing
Threshold-driven requirementsWhen value changes, including by modificationCurrent FAR thresholds tableNew requirement added to the task list before signature
Consent to subcontractBefore award, where the prime requires itPrime contract termsAward blocked until consent is recorded
Invoice coded to a funded lineEvery invoiceCLIN and SLIN funding balancesInvoice held; Finance and Program notified
Burn and forecast triggersEvery time-and-materials invoiceCeiling, plan, and site-mix forecastAlerts at 75%, 85%, or forecast above ceiling
Reporting and evaluation due datesDailySubcontract milestones and report schedulesReminder, then escalation if overdue
The judgment call

Automate the checks, not the judgment.

ChallengeA system that decides everything hides its reasoning, and the rules go stale when the FAR changes.

DecisionRules block, flag, and remind. People make the calls, like responsibility and price reasonableness. Compliance owns the rules tables and updates them whenever thresholds or clauses change.

Drafting

Flow-down matrix: what goes to whom, and why

Each clause is checked against each subcontract's type, value, and work. Illustrative only: real applicability depends on the prime contract, the subcontract's value, and the current FAR.

RequirementEquipmentInstallationTrainingWhy
Equal opportunityYesYesYesRequired in subcontracts generally
Combating trafficking in personsYesYesYesRequired in all subcontracts
Safeguarding contractor information systemsNoYesYesInstallers and trainers handle federal contract information; the equipment supplier only ships
Small business subcontracting planYesYesNo plan · counts toward goalThe two large suppliers exceed the FAR threshold and must have plans. Small businesses are exempt from submitting a plan (FAR 19.702(b)(1)), but Hypothetical Learning's dollars count toward Fauxmed's own small business goal and are reported
Service contract labor standardsNoYesCheckApplies to service work; depends on whether trainers are exempt professionals
Audit and records accessNoYesNoHours billed on time and materials must be auditable
Customer privacy terms for health dataNoYesCheckAnyone who may see patient data; trainers only if live systems are used
The judgment call

"Flow down everything" feels safe. It is not.

ChallengeClauses that do not apply invite redlines, slow negotiation, and push suppliers to price in risk they do not carry. Flow-downs were the second-largest source of redlines in the How I Work: Lean.

DecisionFlow down what is required, plus what this supplier's work actually touches, and document why each "No" is a no.

Negotiation

Installation: opening, target, and where it settled

Targets came from two other quotes, past rates, and Fauxmed's own level-of-effort estimate: 40 clinics at about 275 hours each, roughly 11,000 hours.

TermSupplier openedFauxmed targetSettledBasis
Blended labor rate$112 / hr$98 / hr$101 / hrWithin the range of competing quotes and prior rates
Ceiling$1.35M$1.15M$1.2M11,000 hours × $101, plus an 8% reserve
Per-clinic not-to-exceedNone$32K$35KAnything over needs written approval before work continues
Liability cap1× contract value3×2×Fallback 1 in the approved playbook, logged
Year 2 rate, support option+5% a year+2.5%, matched to the prime+2.5%, same index and timing as the primeEscalation Fauxmed cannot recover from its customer becomes a loss that compounds every year
TravelBilled as incurredFederal travel rates, at costFederal travel rates, at costMirrors how the prime can be reimbursed

Before the first call

Negotiation is decided mostly in preparation. Every point below was written down before the supplier saw a redline.

Target
$98 / hr, $1.15M ceiling
Walk-away
$104 / hr, $1.25M ceiling
Best alternative
Notreal Install Group, ranked second
What Fauxmed can give
Faster payment per accepted clinic
What Fauxmed cannot give
Audit access, mandatory flow-downs

Why the alternative matters

A negotiator with no alternative is just accepting slowly.

Notreal scored within 0.15 points. That made the walk-away number real, and the supplier could tell.

Two rules I negotiate by

Neither is a regulation. They are practices that keep price decisions consistent, explainable, and hard to drift.

Rule 1 · Reasonableness band

Within 10% of our own estimate, either direction

Every proposal is compared to Fauxmed's independent estimate before negotiating. Outside the band, we find out why first. Low bids get the same scrutiny as high ones.

Rule 2 · Authority band

Within 3% of target, the negotiator decides

From 3% to 10% over target, a manager approves and the reason goes in the negotiation memo. Past the walk-away, a director approves, or we walk.

Proposal, blended rateRatevs $99 estimateWhat the review found
Imaginary Field Services$112+13%Travel time was priced into the labor rate. Moved to its own line at federal travel rates, then negotiated.
Notreal Install Group$93−6%Inside the band. No further review needed.
Placeholder Technical$84−15%Too low. Priced 8 hours per site survey against a 24-hour requirement. A misread scope, not a bargain.
The rule in action

Settled at $101 against a $98 target: 3.1% over. One dollar past the line, so it went up for approval.

ChallengeThree dollars an hour sounds small. Across 11,000 hours it is $33,000. But "close enough" every time is how a portfolio overpays.

DecisionThe manager approved it on the record: the rate was still 2% above the estimate and inside the band, and Imaginary's multi-site past performance was the reason it won. Fauxmed's offers moved $95, $98, $100, $101, shrinking steps that signaled the limit without having to say it.

What the supplier's redlines flagged, and how each was handled

Each supplier ask was sorted before responding: terms Fauxmed must hold, terms it can trade, and risks it accepts but mitigates. Treating them all the same either gives away what cannot be given or fights over what does not matter.

Hold

Not negotiable

Required by the prime contract or regulation. Explain why, offer flexibility in how it is met, and walk away if refused.

Trade

Give to get

Use the approved playbook ladder, and never concede without getting something back.

Accept and mitigate

Manage it instead

Not worth the fight on paper. Reduce it in practice with insurance, buffers, or oversight.

  1. 01

    "We will not accept the audit and records clause."

    RiskFauxmed could not support its own time-and-materials billing to the customer, and the clause is required.

    NegotiateHold. Explain that it comes from the prime contract. Offer flexibility on how, not whether: records limited to this subcontract, reasonable notice, at the supplier's site.

    If refusedWalk away to the second-ranked bidder. This is the one ask with no mitigation.

  2. 02

    "Liability capped at one times fees, all damages excluded."

    RiskFauxmed stays fully liable to the customer. A low cap downstream with no cap upstream leaves Fauxmed holding the gap, including for a data breach.

    NegotiateTrade. Move to the playbook's 2× cap in return for faster payment, but keep data breach, bodily injury, IP, and gross negligence uncapped.

    MitigateRequire cyber liability insurance naming Fauxmed, and supervised access to clinic systems.

  3. 03

    "Termination for convenience pays our anticipated profit."

    RiskIf the customer terminates Fauxmed for convenience, Fauxmed generally does not recover profit on work never performed. Promising it downstream creates a loss Fauxmed cannot pass on.

    NegotiateHold the principle, mirror the prime: costs incurred, reasonable profit on work done, and settlement costs.

    GiveA longer notice period, which costs Fauxmed little and matters to the supplier's crews.

  4. 04

    "We may substitute key personnel at our discretion."

    RiskThe project manager who won the evaluation could be swapped on day one, and the customer may have relied on that person too.

    NegotiateTrade. Named key personnel, 15 days' notice, equal or better qualifications, and Fauxmed approval that will not be unreasonably withheld.

    MitigateA backup installer pre-qualified before award.

  5. 05

    "Work directed by any Fauxmed staff is billable."

    RiskA program manager saying "while you're here" on site becomes billable scope with no modification and no funding.

    NegotiateHold. Only the Subcontracts administrator can authorize changes, in writing.

    MitigateBrief Program staff on the rule, and log every change request, even the ones declined.

  6. 06

    "Equipment delivery dates are estimates only." (Sampleton)

    RiskFauxmed's delivery dates to the customer would rest on dates nobody promised, with install crews waiting on pallets.

    NegotiateTrade. Firm dates per wave, a 10-day cure period, and the right to buy elsewhere and charge the difference, in exchange for Sampleton choosing its carrier.

    MitigateA two-week buffer between delivery and install, and the corrective action process if a wave slips.

Every settled term is recorded in a negotiation memorandum with the basis for it, so anyone reviewing the file later can see why the number is reasonable, not just what it is.

Deliverables and milestones

Training: payment follows proof

Each milestone has acceptance criteria and the evidence that proves it, written into the subcontract before work starts.

MilestoneAccepted whenEvidencePayment
1 · Training planApproved by Fauxmed's program managerSigned approval10%
2 · Curriculum and materialsReviewed against the pumps' clinical workflowsReview checklist, final files20%
3 · Wave 1, 14 clinicsEvery scheduled session deliveredAttendance records, session sign-offs25%
4 · Wave 2, 13 clinicsSame as wave 1Attendance records, session sign-offs20%
5 · Wave 3, 13 clinicsSame as wave 1Attendance records, session sign-offs20%
6 · Final reportAt least 90% of staff pass the competency checkCompetency results by clinic5%
Compliance file

Before signature: the audit-ready file

Everything a purchasing system review or a customer audit would ask for, in the file before the subcontract is issued.

  • Exclusions check dated just before awardNot only at proposal
  • Responsibility determination documentedCapacity, integrity, financial health
  • Small business status verifiedAgainst the supplier's federal registration
  • Consent to subcontract obtainedWhere the prime contract requires it
  • Price reasonableness documentedNegotiation memorandum and basis
  • Conflict of interest screenSupplier and evaluators
  • Flow-down matrix with reasonsIncluding every "No"
  • Concessions logged against the playbookVersion and approver recorded
The judgment call

A file assembled when the auditor arrives is a reconstruction.

ChallengeUnder deadline, it is tempting to issue the subcontract now and finish the paperwork later. Later rarely comes.

DecisionThe complete file is a gate. The subcontract cannot be issued until every item is checked, so the file is always audit-ready, not made audit-ready.

How I got there

  1. Mapped every required check to its FAR source, and turned the checks into system rules that block, flag, and remind, the same pattern as the automated approval workflows I built in Oracle APEX.
  2. Built the flow-down matrix clause by clause, with a reason for every no.
  3. Ran every proposal through a reasonableness band and every settlement through an authority band, so price decisions are consistent and explainable.
  4. Negotiated from an independent estimate and a real alternative, with target and walk-away set before the first call, and documented the basis for each settled term.
  5. Sorted every redline before answering it: hold, trade, or accept and mitigate, so required terms were never traded and minor ones never stalled the deal.
  6. Tied every payment to evidence, and kept the largest payments for delivered training, not paperwork.
  7. Made the audit-ready file a gate before signature, not a scramble before an audit.

Stage 03 · Post-award

After signature, the work is watching, early.

Most subcontract problems are visible months before they become expensive. The job is to build the views that show them, and the relationships that make raising them normal.

What this shows

Working across functions with clear ownership, forecasting time-and-materials burn instead of only tracking it, and grading suppliers against criteria they saw on day one.

Working cross-functionally

Who owns what across the subcontract's life

R does the work, A owns the outcome, C is consulted, I is informed. One A per row.

ActivityProgramSubcontractsFinanceLegalQuality
Statement of work and requirementsARCCC
Source selectionRARIC
Flow-downs and draftingCAIRI
NegotiationCACCI
Milestone acceptanceARIIR
Invoice approvalRCAII
ModificationsRACCI
Performance evaluationRACIR
Funds traceability

Every dollar lands on a contract line

The task order is priced and funded by contract line item (CLIN) and subline (SLIN). Every subcontract dollar maps to one, and every invoice must cite the line it bills against. As of month 6.

CLIN and SLINsTypePrime valueSubcontractSub valueInvoicedRemaining
0001 Infusion pumps0001AA to AC, one per waveFixed price$4.65MSampleton Devices$4.10M$2.73M$1.37M
0002 Installation0002AA labor, AB travel, AC materialsTime and materials$1.62MImaginary Field Services$1.40M ceiling$0.83M$0.57M
0003 Training0003AA to AF, one per milestoneFixed price$0.45MHypothetical Learning$0.38M$0.29M$0.10M
0004 Program managementFixed price$0.60MFauxmed staff, not subcontractedn/an/an/a
The judgment call

"It's fixed price, so nobody audits it" is half true, and the wrong half to rely on.

ChallengeOn fixed-price lines the customer generally pays for delivery, not for the supplier's costs. On time-and-materials lines, billed hours and rates are open to audit.

DecisionTrace every dollar either way. Fixed-price invoices tie to an accepted delivery or milestone on a funded SLIN. Time-and-materials invoices also tie to timesheets, negotiated rates, and receipts. No invoice is paid against a line without funds.

Tracking and reporting

Time-and-materials burn: forecast, not just spend

Installation spending against the $1.2M ceiling. The dashed line is the plan; the solid line is actual; the copper line is the forecast at completion.

ceiling $1.2M85% decision point75% notify0$0.5M$1M$1.5Mforecast $1.385Mactual $830K, month 6plan12345678910month of performance
Spent by month 6
$830K, 69% of ceiling
Clinics complete
22 of 40, 55%
Pre-1990 clinics, average cost
$55K, needed electrical upgrades
Newer clinics, average cost
$26K
Forecast at completion
$830K + (3 × $55K) + (15 × $26K) = $1.385M
The judgment call

Spend was only 69% of the ceiling. The 75% trigger had not fired. The subcontract was already in trouble.

ChallengePercent-spent triggers are lagging. They fire after the money is gone. Spend was outrunning progress: 69% of the money for 55% of the clinics.

DecisionForecast by site mix, not by average. Older clinics cost twice as much, and only 3 remain. The overrun came from unforeseen site conditions, so Fauxmed requested an adjustment from the customer, and raised the subcontract ceiling to $1.4M only after the prime modification was signed.

Never obligate a supplier beyond what the prime contract funds.

Notify trigger75%Program and Finance review the forecast
Decision trigger85%Modify, re-scope, or descope
Forecast triggerEAC > ceilingAct now, whatever the percent spent

The monthly subcontract report carries the same view for all three suppliers: spend against plan, forecast at completion, milestones accepted, open modifications, and small business reporting status.

Changes and modifications

No work on a change until the change is on paper

Undocumented changes are how scope creeps, invoices get disputed, and a supplier ends up working beyond what the prime contract funds.

  1. Change requested

    By the supplier, Program, or the customer, in writing.

  2. Impact assessed

    Cost, schedule, flow-downs, and whether the prime contract covers it.

  3. Funding confirmed

    If it is new scope, the prime modification comes first.

  4. Modification issued and logged

    Signed by both parties, then work begins.

Modifications issued4Including the installation ceiling
Average days to execute6Request to signature
Work without a modification0On target
Small business reporting

Goals tracked, not reconstructed at reporting time

Choosing a large installer over a small one in Stage 01 put the small business goal at risk. Tracking it monthly showed the training subcontract alone would keep it on target.

Goal, share of subcontract dollars to small businesses
5%
Actual to date
6.7%
Reports filed on time
All, on the required schedule
Performance grading

How the grading criteria were built

The supplier's grade mirrors how the federal customer grades Fauxmed: quality, schedule, cost control, management, and compliance. If a supplier's work drags Fauxmed's rating down, the supplier's own scorecard should show it first.

Schedule scoreWhat earns it
5 · ExceptionalEvery milestone on time or early, with no Fauxmed intervention
4 · Very goodAll milestones on time; minor slips recovered within the same month
3 · SatisfactoryUp to 10% of milestones late, each with an accepted recovery plan
2 · MarginalMore than 10% late, or a recovery plan missed
1 · UnsatisfactoryA late milestone delayed the prime contract's delivery to the customer

Every factor has a rubric like this one, tied to evidence anyone can check, so two reviewers grading the same supplier land on the same score.

Supplier, quarter 2QualityScheduleCost controlManagementComplianceOverall
Sampleton Devices545444.4
Imaginary Field Services442443.6
Hypothetical Learning555454.8

Imaginary's cost score reflects the burn overrun, even though the cause was outside its control. The score records what happened; the written comments record why. Both go into the review.

Relationships

A rhythm that makes bad news early and routine

  1. Weekly

    Operations call

    Program and supplier leads. Schedule, blockers, next two weeks.

  2. Monthly

    Subcontract status

    Burn, forecast, invoices, modifications, compliance items.

  3. Quarterly

    Business review

    Scorecard reviewed with supplier leadership before it is final.

  4. Any time

    Escalation

    A set path with time limits, so no issue waits on a calendar.

2 business daysWorking leads→5 business daysSubcontracts manager and supplier PM→10 business daysDirectors on both sides

When performance slips

Each step is documented, so if a relationship does end, the record shows it was handled fairly.

Step 1Raise it in the weekly call→Step 2Corrective action request: root cause and plan in 10 days→Step 3Formal cure notice, with Legal→Last resortTermination, with a backup ready

Used once: Sampleton's second wave shipped without mounting kits for four clinics. The corrective action request was closed in three weeks with a packing check added at its warehouse, and its schedule score of 4 reflects a slip that was caught and recovered.

No surprises in the scorecard. Suppliers see the grading criteria at award and their draft score before it is final. A grade they can predict is a grade they can improve.

How I got there

  1. Gave every cross-functional step exactly one owner, so invoices, acceptance, and modifications never stall between teams.
  2. Traced every dollar to a funded contract line, with the evidence each contract type requires.
  3. Forecast at completion from the actual site mix, which caught the overrun before the percent-spent trigger did.
  4. Built grading criteria from the prime contract's own evaluation factors, with evidence-based rubrics.
  5. Kept changes on paper before work, and tracked small business goals monthly instead of at reporting time.
  6. Set a meeting rhythm, an escalation clock, and a corrective action path so problems surface while they are still cheap and are handled fairly when they do.

Stage 04 · Closeout

Closeout criteria are written at award, not discovered at the end.

If nobody defines "done" until the work is over, closeout turns into months of chasing signatures and reconciling invoices from memory. Every item below was in the subcontract from day one.

What this shows

A closeout built into the subcontract at award, with an owner and evidence for each item, and extra checks where time-and-materials billing creates extra risk.

Closeout checklist

All subcontracts need the checked items. Time-and-materials subcontracts also need the items marked with a plus.

  • Every deliverable and milestone acceptedProgram · signed acceptances
  • Final invoice received and reconciledFinance · matched to payments and acceptances
  • Release of claims signedSubcontracts · no open disputes remain
  • Fauxmed property and data returned or destroyedProgram · certificate of return or destruction
  • Final small business report filedSubcontracts · where a plan applied
  • Final performance evaluation sharedSubcontracts · supplier acknowledged
  • Unused funds releasedFinance · so they can return to the prime contract
  • File complete and retainedSubcontracts · for the required retention period
  • Billed hours audited against timesheetsFinance · sample tested
  • Billed rates checked against negotiated ratesFinance · every invoice
  • Ceiling reconciled to final spendSubcontracts · including every modification
  • Travel checked against federal ratesFinance · receipts on file
The judgment call

Close each subcontract when it is done, not when the task order ends.

ChallengeWaiting to close all three together felt efficient. It would have left the training subcontract open for nine extra months, with funds tied up and records going stale.

DecisionTraining closed within 60 days of its final milestone, and its unused funds went back to the prime contract to help cover the installation adjustment.

How I got there

  1. Wrote "done" into the subcontract at award, with an owner and evidence for each item.
  2. Added extra checks where the contract type adds risk, because billed hours and rates are where time-and-materials closeouts go wrong.
  3. Closed each subcontract on its own schedule, freeing funds and keeping records fresh.

What leadership sees: the portfolio view

One screen for a VP, at month 14: is the subcontract portfolio on track, on budget, and compliant?

Milestones on time94%One slip, recovered
Invoices paid within terms97%Suppliers paid reliably
Forecast vs funded ceiling$1.385M / $1.4MWithin funding
Audit findings0File complete at signature
Small business share6.7%Goal 5%
Subcontracts closed1 of 3Training closed in 60 days

Three suppliers. Forty clinics. One set of promises, kept by people who never signed the prime contract.

That is subcontract management: choosing well, writing it down precisely, watching early, grading fairly, and closing cleanly. The paperwork is how the trust holds up.

Fauxmed Supply Co. is fictional. The methods are real. See How I Work: Lean for how I improve a process end to end.

"Excellence is never an accident; it is the result of high intention, sincere effort,
intelligent direction, skillful execution and the vision to see obstacles as opportunities."

— ANONYMOUS
LET'S CONNECT

Have a Complex Problem Worth Solving?

I'm always open to conversations about contracts, operations, process transformation, systems improvement, and meaningful work where better structure can create better outcomes.